Property Issues About The Site Booked


15-Aug-2023 (In RERA Law)
As I have booked the site in IVC telcom city in IVC road devanahalli Bangalore on 2015 they told that they will hand over the layout with in one year till then they have not done any progress to the land we have already paid the amount of Rs
Answers (2)

Answer #1
510 votes
you can approach the rera seeking refund or compensation or possession etc, but you have to be careful, need to check whether the project is covered under rera , approach advocate for detail opinion.
Helpful? LawRato LawRato
Answer #2
735 votes
It is a clear case of delay of handover of possession. You can file a case in RERA or Consumer Commission. You will also be eligible for delay compensation and interest on the amount paid.
Consult a lawyer asap.
If you have any queries, I'm just a call away.
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.