I had purchased 4 shops at vasai in 2018 and as per agreement possession date is 2018. I have made full payment in 2018. What legal option i have in rera so that i get my possession and compensation.Also how is compensation calculated ?
Well, you can file a case before MAHA RERA on the ground of delayed possession. You can seek getting interest until you receive possession of the shops or else, if you do not want to seek possession of the shops and want to withdraw from the project, you can do so by seeking refund of the entire amount invested by you to purchase the shops along with Interest under Sec 18 of the MAHA RERA Act.
since you have a registered agreement you have a good case on merit and if the project is registered with MahaRERA then you can seek interest for delay interest under section 18 of the RERA by filing a complaint before MahaRERA. Interested will be calculated on the amounts paid less taxes at SBI mclr plus 2 percent form the date of payments till possession.
Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.
Connect with top RERA lawyers for your specific legal issue
No Comments! Be the first one to comment.
"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."
682+ Lawyers are online