Flat Allotment Terminated By Builder


07-Jul-2024 (In RERA Law)
I have a flat in a under construction project. The builder buyer agreement has been signed. Total I paid around 40 lacs. Due to delay in payments, the builder has terminated the allotment as per terms of the agreement. What are my options now ?
Answers (2)

Answer #1
817 votes
if the project is approved in RERA you should go legal as per RERA guidelines by raising a dispute in this regards other wise as per relevant sections. they can not forfeit amount you have enough legal remedies for relief
Helpful? LawRato LawRato
Answer #2
770 votes
We can immediately serve them with a legal notice seeking refund of the amount paid along with interest, however, if they do not respond then we can file a complaint before the RERA authority within the appropriate jurisdiction seeking refund of the amount paid with interest
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?