Hello,
Recently, I booked a flat in an apartment which is 80% complete and builder had promised to give the posession by December 2025. I have paid 60% of the flat charges, got the agreement for sale registered and as per schedule, I should be paying another 20% to him. I have just learned that project has been halted due to a financial issue. The builder has a loan of 2 crore and is unable to pay the EMIs. There is absolutely no clarity on when he will complete work and asking me to pay 20%
Since you already have a registered Agreement for Sale and have paid 60%, the builder is contractually bound under MOFA/RERA to complete the project as per promised timelines. The fact that the project is halted due to his private financial issues and unpaid bank loan is no excuse in law. You must not pay the next 20% unless there is visible construction progress and statutory demand notice strictly linked to the registered payment schedule. further answers r required on -
Have you personally visited the site in the last 30 days? Do you have photographs/videos showing the present stage of construction? When was the last time you saw actual labour/material work happening? Did the builder or site engineer officially inform you that construction is stopped? Are other buyers also reporting the same? Do you have any written/WhatsApp proof from them? What is the exact possession date mentioned? Is there a grace period? 7. Is your payment plan construction-linked or time-linked? What clause is written regarding builder’s default/delay? (interest, refund, compensation). Is there any force majeure or financial difficulty clause. How did the builder demand the next 20%—written demand letter/email or verbal call? How did you learn the builder has a ₹2 crore loan and is defaulting on EMIs?Do you have any written proof of this loan default (bank notices, newspaper reports, other buyers’ info)?Have you checked if any encumbrance or charge is registered against the land/project?
If you are sure that the project is halted, you can stop the payment and request refund of all the money that you have paid to the builder after the date possession as per agreement has passed. You will refund with interest. Please note that you can only file if date of possession as per agreement has passed and not promised possession date.
You can file a complaint against the builder on Real Estate Regulatory Authority for delay in possession as per agreement and before filing a complaint send him a legal notice. Also, you can try to settle the matter as 80% of the project is already completed and if the builder is ready to give the possession and you are ready to pay 20%, take the possession first then, if there is a delay you can file a complaint after the possession is taken by you for the delay.
Well, If the Project is registered under RERA, then, you can file a case before the concerned RERA Authority either to withdraw from the Project by taking your whole investment back along with interest or to continue with the project and keep on receiving Interest+ Rent until receiving of final order.
Disclaimer: The above query and its response is NOT a legal opinion in any way
whatsoever as this is based on the information shared by the person posting the
query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to
address the specific facts and details.