I am purchasing the flat from builder before three years he is not registered with maharera. builder is not giving possession every time he is saying we will give possession but he is not giving now I want to cancel the flat and I want money back what action can I take please suggest me
Answers (5)

Answer #1
773 votes
You need to issue a legal notice and file complaint under the consumer protection act. Since the developer is not registered with MAHARERA you need to file suit for specific performance act and seek damages and compensation from the Developer. If you intend to cancel the agreement you need to issue notice for cancellation of agreement for sale and there after file a suit for cancellation.
Helpful? LawRato LawRato
Answer #2
767 votes
kindly consult with an advocate in person and in detailed kindly consult with an advocate in person and in detailed kindly consult with an advocate in person and in detailed kindly consult with an advocate in person and and detailed
Helpful? LawRato LawRato
Answer #3
540 votes
You can cancel due to delay and non-registration under MahaRERA. Issue legal notice, file complaint before MahaRERA for refund with interest, or approach Consumer Court for deficiency of service and unfair trade practice.
Helpful? LawRato LawRato
Answer #4
948 votes
Since the builder is not registered with MahaRERA and has delayed possession for years, you can cancel the booking, issue a legal notice, and file a complaint before MahaRERA and Consumer Forum seeking refund with interest and compensation.
Helpful? LawRato LawRato
Answer #5
609 votes
Your case is legally strong. If the builder is not registered under MahaRERA and has delayed possession for three years, this amounts to serious statutory violation and breach of contract. Under the Real Estate (Regulation and Development) Act, 2016: 1. Every project exceeding the prescribed limit must be registered with MahaRERA. 2. Failure to register itself is punishable. 3. Delay in possession gives you the right to: • Withdraw from the project, and • Claim full refund with interest and compensation. You have the following legal remedies: 1. File Complaint before MahaRERA Even if the project is unregistered, complaint can be filed. MahaRERA can impose penalty and direct refund with interest. 2. Consumer Commission Complaint Delay in possession is deficiency of service. You can claim refund, interest, and compensation for mental harassment. 3. Civil Suit for Recovery If required, recovery suit with interest. 4. Criminal Action (if fraud is evident) If builder collected money knowing he cannot deliver, criminal complaint under cheating provisions can be considered. Before proceeding, I will need: • Agreement copy (if any) • Payment receipts • Brochure / advertisement • Any written possession commitment • Proof that project is not registered under MahaRERA
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."