Builder admitd flat allotment but not registering or paying compensati


03-Jan-2026 (In Property Law)
I am facing a long pending builder/redevelopment delay. The builder has not obtained a valid Commencement Certificate and construction has not progressed for many years. In 2024, the builder gave me a written and notarised MOU admitting liability, allotting a specific flat with area, and agreeing to monthly delay compensation. However, the agreement is not being registered and compensation is unpaid, citing absence of CC. What is the correct legal step now under RERA? Can I seek interim compensa
Answers (5)

Answer #1
647 votes
File a complaint with RERA for delay & non-payment. Seek interim relief for compensation under Section 18. The notarized MOU is strong evidence of admitted liability. Consult me to file your case as per the concerned provisions of law
Helpful? LawRato LawRato
Answer #2
592 votes
File a complaint under Section 31 RERA for delay and non-payment. Seek interest/compensation under Section 18 and interim relief under Section 38. Absence of CC is no defence. Notarised MOU supports your claim.
Helpful? LawRato LawRato
Answer #3
832 votes
yes, file a Complaint under provisions of RERA before the RERA Authority and also consumer court and you can seek, Monthly delay compensation / interest and order to obtain CC within a time-bound period, Registration of agreement for sale, Penalty for non-compliance Alternatively, refund with interest. and also seek interim relief on the besis of MOU.
Helpful? LawRato LawRato
Answer #4
885 votes
yes you can file a case against the builder in RERA, if they have not given you the possession as per the documents with or without MOU, the builder is bound to give you compensation, and interest for the delayed period.
Helpful? LawRato LawRato
Answer #5
645 votes
Since your builder has: Not obtained a valid Commencement Certificate (CC), Not progressed with construction for several years, and Signed a written and notarised MOU in 2024 acknowledging liability, allotting a flat, and agreeing to monthly delay compensation, you have strong legal remedies under Maharashtra RERA (or your state RERA): File a Complaint under RERA: You can approach the RERA Authority for: Specific performance of the allotment as per the MOU Payment of delay compensation Directions for the builder to register the allotment/possession Interim Relief / Compensation: RERA allows you to seek interim relief even before the final order. You can request the Authority to direct the builder to pay delay compensation as per the MOU. Courts and RERA authorities often grant interim compensation based on admitted liability, even if the CC is pending. Supporting Documents: Copy of MOU/notarised agreement Correspondence with builder Proof of delay Original allotment details and payments made ✅ Bottom Line: You can directly approach RERA, seek interim compensation, and compel the builder to perform obligations under the notarised MOU, despite non-registration, because RERA protects the homebuyer’s rights. If you wish, we can consult in detail, review your MOU, and assist with filing the RERA complaint and claiming interim compensation, to ensure the builder complies promptly. Regards, AARS Legal Associates Advocate Sumaiya Parvin
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.