Hi. I purchased flat in Navi mumbai under maha Rera from a reputed builder group 1.5 years ago. However during the initial sale discussion it was said the possesion would be December 24. However from June I realised there was not much progress and hardly any work is going on. October 2024, they mentioned they are waiting for cc approval for additional 2 floors. But the floor plan when I booked is of 12 floors &to my shock no one communicated this. Now the possesion date is October 2025. Help?
Answers (4)

Answer #1
674 votes
It is illegal to modify the development plan without any intimation and consent of the flat purchasers and unilaterally. You can legally challenge the said modified development plan. Feel free to contact me for seeking any legal advice as regards the same.
Helpful? LawRato LawRato
Answer #2
878 votes
Well, if already too much delay has been caused in getting the Project ready and to be delivered to you in terms of Possession, then, you can file a case before the concerned RERA Authority to seek refund of the whole investment made by you along with interest on the ground of Delay happening in giving you Possession or you can wait and keep on receiving Interest from the concerned Builder until and unless your flat becomes fit to be occupied by you with the completion of whole Project.
Helpful? LawRato LawRato
Answer #3
666 votes
Send a legal notice to the builder demanding an explanation for the delay, unapproved additional floors, and compensation for the inconvenience caused. Seek interest for period of delay or refund with interest. File a formal complaint with MahaRERA (Maharashtra Real Estate Regulatory Authority) under Section 31 of the RERA Act, 2016. The builder's failure to provide possession on the agreed date and uncommunicated changes to the project are clear violations. The delay caused by this is not justifiable, and this can be emphasized in your complaint.
Helpful? LawRato LawRato
Answer #4
533 votes
Well, you can file a case before MAHA RERA if you are based in Maharashtra to seek whole refund of Investment made by you along with Interest + Compensation, that is, to withdraw from purchasing flat in Project or another option which you can choose is to keep on getting Interest on monthly basis until you get the possession of flat in such Project in which you have invested your hard earned money.
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."