Builder is not giving possession and delay penalty


20-Feb-2023 (In Property Law)
How can I compel to give delay penalty which they are ignoring and not paying.
Answers (3)

Answer #1
986 votes
claiming interest for the delay which has occasioned in handing over of the property/flat is your right under the real estate regulatory authority act, more specifically in terms of section 18 and 19(4). file a rera case against the builder
Helpful? LawRato LawRato
Answer #2
692 votes
If the possession is not delivered on time and the builder is also not giving delayed interest then you can file a complaint before UPRERA and UPRERA if satisfied with your submissions will award you delayed interest @MCLR+1%. Kindly visit office for further details
Helpful? LawRato LawRato
Answer #3
922 votes
kindly raise the complaint before RERA and Consumer Forum and seek the relief for delay penalty along with interest at the rate MCLR and the concerned court will provide you the relief after paying the proper court fee..
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.