Sir, I have one question as already mentioned in the query list regarding mobile tower fixing, so i would like to know to which concern authority we need to get permission for to allow mobile tower to plant in our area. Thank you
Answers (1)

Answer #1
582 votes
Mandatory documents / conditions required to be complied with before granting
approval / regularization of proposal.
1) Requirements as per rule 5(3) of D.C. Regulation 1991
a) Key Plan, site plan, block plan etc.
b) Ownership title
c) Location plan
d) Plans of the proposed work
2) The covered area required on top of the terrace for antennae / dish antennae /
communication tower used for Telecom (basic cellular or satellite telephone) or
ITE purposes, V-Sat, Routes, Transponders or similar IT related structure or
equipment, shall be limited to 20.0 Sq.Mt. as per D.C.R. 35(3)(xv). Maximum
one no. of communication tower for one company.
3) Consent from Owner/ N.O.C. from Co-op. Housing Society/ 70% consents of
occupants in case of Apartment or condominium.
4) Copy of License granted by Department of Telecommunication, Govt. of India to
service provider.
5) Structural Stability Certificate from Structural Engineer having License issued by
M.C.G.M. The fresh Structural stability certificate shall be insisted after every 5
years after approval at the time of renewal of proposal in case of building more
than 30 years old.
6) Registered undertaking from company and owner/ society.
a. That the cabin shall not be utilized for any other purpose than the cellular
telecommunication system.
b. That if the said activity is disconnected by the company, the said cabin
shall be demolished forthwith by the company / owner/society.
7) N.O.C. from Civil Aviation Authority if required.
8) Shall not be allowed on Schools, Colleges & Hospitals, the towers will not be
allowed on Children correction homes (Balsudhrgriha), Vrudhashram and
hostels / orphanage buildings for children.
9) Shall not be allowed on any adjoining building within 3m. from building of school/
colleges/ hospital/ Children hostels/ orphanage buildings and the antenna should
not be directed/ positioned towards the these buildings.
10) The existing mobile antenna approved earlier on school/college & Hospital
buildings shall not be renewed further after expiry of period of approval and the
same shall be removed immediately.
11) The cabin may be granted on ground level. However the same shall not be
allowed in compulsory open spaces.
12) N.O.C. from M.C.Z.M. Authority in case of C.R.Z. area.
13) N.O.C. from M.H.C.C. in case heritage building or precinct.
14) N.O.C. from Estate Dept. in case of Municipal leasehold property
15) N.O.C. from M.B.R.& R.Board in case of cess property.
16) Copy of Access Service License / IP Registration Certificate from DoT shall be
submitted.
17) Copy of SACFA (Standing Advisory Committee on Frequency Allocation)
clearance for the said location issued by WPC wing of DoT shall be submitted.
18) Data Sheet with following information shall be submitted.
a. Name of Service provider / Infrastructure provider
b. Location
c. Tower Reference : i) Height, ii) Weight, iii) Ground / Roof top, iv) No of
Antenna planned on tower.
d. At the entry to the terrace where tower is erected, a warning signboard at
the entry to terrace to that effect shall be displayed.
e. The applicant shall submit the Undertaking stating that there shall be no
nearby building right in front of the antenna with height comparable to the
lowest antenna on tower at a distance threshold as specified below.
Sr No No of Multiple Antennas Building/Structure from the antenna (safe
distance) (in meters)
1 2 35
2 4 45
3 6 55
4 8 65
5 10 70
6 12 75
f. The applicant shall also undertake that the provision of mobile tower /
antennas shall be incompatible with the guidelines from the DoT. If at any
stage, it has been brought to the notice of M.C.G.M. by
Telecommunication Enforcement Resources & Monitoring (TERM) Cell of
Department of Telecommunication regarding the same, the mobile tower /
antennae will liable to be removed.
19) The proposal for approval / regularization of mobile tower accepted only is all the
required documents are enclosed alongwith the proposal. On receipt of the
proposal, the same will be processed for approval as per the circular under No.
CHE/23453/DP/Gen dated 24/1/2012. However, in any case the proposal shall
be decided strictly within the period of 60 days.
20) There will be only two towers allowed on one building / wing of the building.

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."