Good evening, My contract was divided into different phases which had to be executed, My contract started in February 2022(had to be completed in 250 days) I have not yet been able to complete phase 1 and my extension ended on 31st july 2023( I will be able to complete it in 2 months). I was forced to start phase 2 as i was not being paid until and unless I start thus I did even though in my contract it was mentioned that i have to start phase 2 after completion of phase 1. Now I have received
Answers (2)

Answer #1
870 votes
Very vague query.
Please mention proper details to get a genuine answer.
You have not mentioned what you have received now
Also please tell what did you have to perform

mention the nature of contract and the exact terms of the contract.
Helpful? LawRato LawRato
Answer #2
502 votes
you can claim the compensation for the woro done, though it all depends on the kind of contract being drafted. if you agreement specifically state about the time period then you might have to contest in a proper manner.
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."