Construction 80% over But Poor quality. Defective construction.


28-Mar-2025 (In Property Law)
Builder agreed for construction at Thirunravur Chennai at Rs 2400 per sqft and agreed Rs 25 lacs. 90% amount paid. Builder demanded more money. Not ready to attend defects. He needs to go out from contract. Bank loan.
Answers (1)

Answer #1
934 votes
1 send a well drafted legal notice should be sent to the builder , demanding - completion of construction as per the agreed price - Rectification of defects - Compensation of delay ( if applicable ) - Refund of excess of money if termination is sought. 2. File a complaint with RERA 3. Consumer comaplint 4 specific performance suit 5 criminal compliant 6. Loan consideration : if a bank loan is involved ensure the bank is informed about the dispute. If necessary , pause disbursement to avoid financial loss
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."