Need legal advice before buying a resale flat in Pune project. Building was completed around 2016, but builder allegedly constructed an unauthorized 11th floor beyond Pune Metropolitan Region Development Authority approved plan. OC, CC, proper possession letter and society formation for this wing are still pending. Residents occupied flats on “Permission to Enter” basis. Is it legally safe to buy? What risks/documents should I check?
Answers (3)

Answer #1
783 votes
Based on the facts stated, purchasing such flat involves significant legal risk as the building allegedly has unauthorized construction, pending OC/CC, and possession given only on “Permission to Enter” basis. Before proceeding, verify sanctioned plans, OC, CC, RERA details, title documents, society formation status, and whether any demolition or regularization proceedings are pending before PMRDA or local authorities. Also check if banks are approving loans for that specific wing/flat, because banks usually detect trouble faster than buyers blinded by “good deal” pricing. If the flat is part of the unauthorized portion, future risks may include demolition, resale difficulties, loan rejection, and litigation. Proceed only after complete legal due diligence through an advocate.
Helpful? LawRato LawRato
Answer #2
514 votes
Dear Client, It is primary to ascertain as to till which floor Construction permission has been granted by the PCMC. Furthermore, since you have mentioned that the builder has constructed unauthorised constructions begs me to ask another question, as to whether you intend to book the flat in respect of the unauthorised construction? Please provide sufficient details in order to arrive at a proper conclusion
Helpful? LawRato LawRato
Answer #3
877 votes
I can help you with this. Based on what you’ve stated, this is a **high-risk purchase** unless the deviations are regularised. “Permission to Enter” is not equivalent to lawful possession, and absence of OC/CC for the wing can affect legality, utilities, loans, resale, insurance, and even expose occupants to demolition/penalty risks in extreme cases. You should verify: sanctioned plans, revised approvals (if any), commencement certificate, OC/CC status, MahaRERA details, conveyance/society status, litigation/notices from PMRDA/PMC, fire approvals, and whether the 11th floor has been regularised or challenged. Do not rely only on builder/seller assurances. A detailed title and compliance due diligence is strongly advisable before proceeding. I can assist in reviewing the project documents and risk assessment.
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.