Delay compensation for a RERA Registered Project


25-Sep-2023 (In RERA Law)
I invested in a property in Pune in August 2018. The project had begun in pre RERA days and had promised some of it's existing buyers completion date of Dec 2016 which it clearly didn't meet. At that time when my agreement was executed ,project was registered with MahaRERA and had a completion date of 31 December 2018. My agreement has a completion date of December 2018 too. They have failed to deliver the flats till now (September 2019) with a lot of construction still to be done. In December 2018 they applied for 1 year extension in RERA and got completion date extended to Dec 2019. Their RERA application currently shows this: Proposed Date of Completion:31/12/2016 Revised Proposed Date of Completion: 31/12/2018 Extended Date of Completion: 31/12/2019 Will I be able to seek damages from builder as he has denied any for Dec 2018 - Dec 2019 period arguing that RERA extension overrides all previous agreements. Will I at least be able get compensation post Dec 2019 or can he extend.
Answers (1)

Answer #1
678 votes
Seeking a remedy from RERA is a grey area. However, he was bound by a contract vide the agreement executed between you and the builder. Please note he has breached the contract by not giving the position within the period in the agreement. A civil suit can be filed. However, the remedy will be at the discretion of the court as RERA has the complete jurisdiction over property matter
Helpful? LawRato LawRato

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."