Delay in flat possession due to floor rise what can i do


03-Dec-2023 (In Consumer Court Law)
I booked flat in Sep-2015 and possession promised in April-2016. Builder decided to increase two more floor in Jan-2016. He informed us in Jul-2016 that he got permission for floor rise and agreed for interest on payment made@9% and he charged interest@24% for delay in payment to demand letter. He paid us interest payment installment due till Sep-2016 in Sep, Oct and Nov as agreed. Still official permission not received for floor rise but they built 11th & 12th floor. Now, when we asked for further interest payment, he sent us demand for final payment with architect certificate for readiness of building till 10th floor issued by architect in Mar-2016 to common chain mail series between builder & flat owners. Please guide us what should be our action plan.
Answers (1)

Answer #1
689 votes
Collect adequate documents to prove your allegations and then file a case before the Local District Consumer Dispute Redressal Forum. Your other flat owners also can join you. As unity is strength. And

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."