How to file complain against the Builder under RERA Act in Bangalore


02-Aug-2023 (In Consumer Court Law)
We have the Apartment Allotment letter, MOU, Sale Agreement and Construction Agreement. The Builder has progressed the construction of the Apartment up to around 75%. Not completing the construction. Schedule date of delivery of Apartment already over. Stopped construction. Not willing to register as ongoing project under RERA Act in Bangalore. Not willing to hand over or register the the apartments to Allottees. Can we get the relief to register the apartment in our name from Regulatory Authority under RERA Act. If so, please advise.
Answers (1)

Answer #1
733 votes
Your builder has just escaped the need to register under RERA as Karnataka Government has exempted those who have completed 60 per cent and above of their project from application of the Act. But you have remedy under other Laws, and can force him to complete.

Disclaimer: The above query and its response is NOT a legal opinion in any way whatsoever as this is based on the information shared by the person posting the query at lawrato.com and has been responded by one of the Divorce Lawyers at lawrato.com to address the specific facts and details.

Report abuse?

Comments by Users

No Comments! Be the first one to comment.

"lawrato.com has handpicked some of the best Legal Experts in the country to help you get practical Legal Advice & help."